SyteLine Planning Workbench Optimization for Production Planners
The SyteLine Planning Workbench is where MRP output meets planner decision-making. After each MRP regeneration, the workbench presents exception messages, planned orders, and action recommendations that planners must review and act on. An unoptimized workbench overwhelms planners with thousands of low-value messages, hiding the critical actions in a sea of noise. Targeted workbench configuration transforms MRP output into an actionable daily planning tool.
Exception Message Filtering and Prioritization
SyteLine MRP generates exception messages for every item where the current plan does not align with demand. Without filtering, a typical manufacturing site sees 5,000-15,000 exceptions per MRP run. Effective filtering reduces this to 200-500 actionable items per planner. The Planning Workbench filter configuration determines which messages surface and in what order.
- Filter by Planner Code to show only exceptions assigned to the current planner's responsibility
- Sort by dollar impact (extended cost x quantity) to prioritize high-value exceptions first
- Exclude reschedule messages within tolerance window (e.g., suppress reschedule <3 days)
- Highlight expedite messages (reschedule-in) separately from defer messages (reschedule-out)
- Filter by exception type: Release, Reschedule In, Reschedule Out, Cancel, showing one type at a time
Planner Workflow and Daily Routine
An effective planner daily routine in SyteLine follows a structured sequence: review critical exceptions, process planned order releases, evaluate reschedule recommendations, and update the planning board. The Planning Workbench should be configured to support this sequence with saved filter views and quick-action capabilities.
- Morning priority review: Release messages for orders due within the planning fence (15-20 minutes)
- Reschedule-in review: expedite actions sorted by customer priority and dollar value (30 minutes)
- Planned order firming: convert planned orders to firm planned orders for the next 2-week horizon
- Reschedule-out evaluation: assess carrying cost vs rescheduling cost for each defer recommendation
- End-of-day update: mark processed exceptions as acknowledged, note action taken in planner comments
MRP Output Analysis and Parameter Feedback
The Planning Workbench also serves as a diagnostic tool for MRP parameter quality. Persistent patterns in exception messages indicate parameter tuning opportunities. If MRP consistently generates reschedule messages for the same items, the root cause is likely incorrect lead times, lot sizes, or safety stock levels rather than genuine demand changes.
- Exception frequency analysis: items appearing in 80%+ of MRP runs need parameter review, not repeated action
- Reschedule volume trending: increasing reschedule count indicates growing MRP nervousness requiring time fence adjustment
- Planned order quantity distribution: excessive small planned orders signal lot size parameters need increase
- Safety stock hit rate monitoring: frequent safety stock consumption indicates safety stock quantity is too low
- Monthly MRP health scorecard: exception count trend, action completion rate, and inventory impact metrics
Turn your SyteLine Planning Workbench from noise generator into decision engine -- our planning experts configure workbench workflows that planners actually use.
Related Resources
SyteLine MRP Parameters Tuning Guide
Optimize SyteLine MRP parameters including order policies, lot sizing, safety stock, and lead times for accurate material requirements planning results.
Infor SyteLineSyteLine Demand Forecasting Configuration Guide
Configure SyteLine demand forecasting with statistical models, forecast consumption, demand management parameters, and accuracy measurement for production planning.