ERP

ERP Cutover Planning Best Practices

The cutover weekend is where months of implementation work either comes together or falls apart. A well-rehearsed cutover plan reduces the average go-live downtime from 72 hours to under 24 hours according to Deloitte benchmarks. Cutover planning is not a single document—it is an orchestrated sequence of 200-500 tasks across data, technical, business, and communication workstreams that must execute in precise order.

Cutover Task Sequencing and Dependencies

Every cutover plan requires a detailed task network with dependencies, durations, owners, and verification steps. Tasks fall into four categories: pre-cutover (weeks before), freeze period (final data loads), cutover weekend (system switch), and post-cutover validation. Critical path analysis identifies which tasks have zero float—any delay on these tasks directly extends the go-live timeline.

  • Pre-cutover tasks: freeze legacy system changes, complete final data extracts, disable legacy integrations
  • Data migration sequence: master data first (items, customers, vendors), then open transactions, then historical data
  • Technical tasks: DNS changes, firewall rules, SSL certificates, print server configuration, SSO updates
  • Verification checkpoints: reconciliation gates after each major data load before proceeding to the next
  • Communication milestones: hourly status updates to the war room, pre-scheduled stakeholder notifications

Cutover Rehearsal Strategy

Organizations that conduct at least two full cutover rehearsals are 3x more likely to go live on time. The first rehearsal identifies task sequence errors, missing dependencies, and unrealistic duration estimates. The second rehearsal validates that fixes work and establishes accurate timing baselines. Each rehearsal should mirror production conditions as closely as possible, including weekend scheduling and actual data volumes.

  • Rehearsal 1 (T-8 weeks): full rehearsal with production-scale data to identify sequencing issues and timing gaps
  • Rehearsal 2 (T-4 weeks): refined rehearsal incorporating all fixes, establishing the final baseline timeline
  • Mock rehearsal (T-1 week): abbreviated walkthrough focusing on critical path tasks and communication flows
  • Document lessons learned after each rehearsal and update the cutover runbook within 48 hours

Rollback Planning and Go/No-Go Decision Points

Every cutover plan must include a viable rollback strategy with clearly defined trigger points. The point of no return—typically when open transactions have been migrated and legacy integrations disabled—must be explicitly identified. Before reaching this point, the cutover lead must have authority to execute rollback if critical issues are detected.

  • Define 3-4 go/no-go checkpoints during cutover with specific pass/fail criteria at each gate
  • Point of no return: typically 60-70% through the cutover timeline, after transaction migration begins
  • Rollback procedure: documented, tested steps to restore legacy system within 4-8 hours if triggered
  • War room protocol: continuous monitoring with 15-minute status cycles and immediate escalation paths

Generate an AI-optimized cutover plan with task sequencing and dependency mapping—try Netray's planning agents.